Timeline
1993:
- OCTOBER: Inaugural meeting of the Society held. Site procured cnr. Spring and Main Streets Sheffield
- NOVEMBER: Old Sheffield railway station moved to the site. Site officially opened
- DECEMBER: Laying of the track began. Restoration of the Sheffield Railway Station began.
1994:
- FEBRUARY: First rolling stock moved to the site
- MARCH: first SteamFest held. First running weekend 30 March 1st April
- SEPTEMBER: Given an 115 year old house to put on the site.
- NOVEMBER: All capital construction stops. Lengthy legal manoevres begin.
1996:
- FEBRUARY:Planning Approval for the first stage of planned development obtained…we could only build 1km of track. (read the book!)
2004:
- The group completed 8 x 15m extensions (cost $14,000) on both sides of our locomotive shed to create a workshop and museum.
2008:
- The completion of the Caretakers Cottage and the first stage refurbishment of the station to include a café.